TotalChoice will be performing emergency maintenance on the primary UPS system between 7:00PM and 9:00PM on April 22nd.

 

The primary UPS is experiencing a thermal problem with one of two internal KHL breaker frames. We will be placing the UPS into full maintenance bypass while the problematic breaker is replaced. There is no downtime expected due to this work, but the UPS system will be offline during the window. We will be placing the facility on generator power for the duration of the work as a precautionary measure against any utility interruptions.